1 5-9-07 to 7-9-07 |
Confirm that students have a valid product relating to their Product Study. Encourage to obtain information on design, material and manufacturing issues. |
Welcome and Coursework intro. Criteria for a viable project and how to start finding a situation. |
|
|
2 10-9-07 to 14-9-07 |
Continue with the product study, to produce a Word document which has an introduction and aim and a plan of action. |
Investigation and Clarification of Problems. Situation and Brief Page layout.
|
|
|
3 17-9-07 to 21-9-07 |
Encourage students to implement the plan of action and obtain the required design and manufacturing information. |
Mood Board Plan of Action Brainstorm |
|
|
4 24-9-07 to 28-9-07 |
Emphasize the need to understand that the product under study is a result of interaction with designers and manufacturers. Material choice may be affected by both issues. |
Existing Products Research and Evaluation. |
|
|
5 1-10-07 to 5-10-07 |
Give feedback on the Product Studies and suggest modifications where appropriate. Refer to Specification sheets to ensure appropriate depth of information is obtained |
User and Target Market, Research/Lifestyle Assessment |
|
|
6 8-10-07 to 12-10-07
|
Product study – Design information completed. + info on materials used. |
Demands of your chosen Market, Design Objectives |
Grade Order Thursday 11th. Oct. |
|
7 15-10-07to 19-11-07 Half – Term next fortnight |
Product Study – Manufacturing information to be completed for after Half Term. |
Specification, (Half term homework - Initial Ideas 4 Main Developed ideas) |
|
|
8 5-11-07 to 9-11-07 |
First draft of Study with designing and manufacturing issues – start feedback. |
Finishing and scanning of Initial Ideas and 4 Main Developed ideas. |
|
|
9 12-11-07 to 16-11-07 |
Feedback on Studies and suggested improvements. |
Design Selection, Analysis, Suitable Material Research, Methods of Production. |
|
|
10 19-11-07 to 23-11-07 |
How can the Studies be extended? SWOT analysis for the product. |
Dimensions and Proportions, Technical Data, Orthographic Projection, |
|
|
11 26-11-07 to 30-11-07 |
Further work on completing Product Study. |
Pro Desktop , Exploded 2D/Pro D |
Grade Order Thursday 29th. Nov |
|
12 3-12-07 to 7-12-07 |
First Draft of complete Product Study. |
3D Model of all or part of your design. |
|
|
13 10-12-07 to 14-12-07 |
Feedback for studies. |
Comprehensive Plan for All Stages of Designing and making, Quality Control/Quality Assurance, Batch Production Techniques and Commercial Practices.
|
|
|
14 17-12-07 to 19-12-07 |
Preparing final Product Study. |
Finish above and hand in for preliminary marking. |
|
|