About Us  Support Material  Students Work  Careers Advice  Former Pupils  Links

Year 11 has a strong focus on coursework and students follow a strict plan to ensure that all aspects of the specification are met. Below is a brief outline of each section and dates for completion.

Week

Progress with Coursework

Comments

1   5-9-07 to  7-9-07

Complete the initial design ideas of your casing and then develop in detail four  other designs showing realistic and achievable options.

This is the stage you should be at when you return to school in September

2   10-9-07 to 14-9-07

Complete four designs and show how the circuit board can fit inside the case.

These must be detailed and contain a 3D drawing.

3   17-9-07 to 21-9-07

Compare  your designs with the casing specification and select one as being the most appropriate choice and state why.

Allow for the fixing of the board in the case. Make sure that you have an  On/Off switch.

4   24-9-07 to 28-9-07

Research the Materials required for your case, and the processes required to make it.

 

5  1-10-07 to 5-10-07

.  Plan out the sequence of events to making the casing of your design, include time estimates.

Assessment up to this point.

Marks in this week for Grade order next week.A complete copy of your Powerpoint is required  to be assessed

6 8-10-07 to 12-10-07

 

 

Thursday 11th. October Grade Order marks entered

Make models of the casing to check that all will fit together. Cardboard or Styrofoam.

Check to make sure that the design is ergonomically sound.

7  15-10-07 to 19-11-07

 Half – Term next fortnight

Produce working drawings of the parts to your design – Orthographic Projections. Request materials and begin making.

Any parts to be cut out using the laser cutter, must be drawn using 2D Design.

8  5-11-07 to 9-11-07

Pro Desktop or Techsoft 2D Designs. Photograph the tools and processes you use during the making of your  casing

Remember allow at least 3 weeks for the painting of your project if you are using MDF or wood.

9  12-11-07 to 16-11-07

Making – documentation – Full planning showing evidence of planning before making begins. Estimate time allowed for each part of the making process and state what tools, materials and other resources you require. This section must appear it will cost you marks if it is omitted

.

10  19-11-07 to  23-11-07

Making & modifying - documentation Assessment up to this point.

Marks in this week for Grade order next week.A complete copy of your Powerpoint is required  to be assessed

11 26-11-07 to 30-11-07

Thursday 29th. November Grade Order marks entered

Making & assembly - documentation

 

12  3-12-07   to 7-12-07

Testing for quality –ensure that you have a good quality finish on the visible pieces.

Photograph each stage of the making

13 10-12-07 to 14-12-07

Making and modifying – testing and evaluating. Keep the documentation up to date

 

14 17-12-07 to 19-12-07

Testing and modifications.

Photograph each stage of testing

  Christmas Holidays

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Easter Term

Progress with Coursework

Comments

14  8-1-08 to 11-1-08

Making should be fully completed now and photographs should be taken of your device in use.

 

15 14-1-08 to 18-1-08

Keep the documentation up to date- record of making.

Mock Examinations begin 18th. Jan until Friday 25th. Jan

16  21-1-08 to 25-1-08

Complete the drawings of your design, including any modifications made.

Assessment up to this point.

Marks in this week for Mock results next week. A complete copy of your Powerpoint  is required  to be assessed

17  28-1-08 to 1-2-08

Check the sequence of making in your planning corresponds with the way you actually made your construction. Modify if necessary.

 

Mock Grades entered 30th Jan

18 4-2-08 to 8-2-08

Week leading up to half - term

Full testing procedure – with photographs of your construction in use. Evaluate using feedback from the user.

 

19 18-2-08 to 22-2-08

 

 

Full comparison of your finished design with the Specification.

Any suggested modifications considered after testing and after receiving the views of others. Assessment up to this point.

Work will be assessed here and if you are not up to date Parent’s will be contacted  expressing our concern about  you not completing your Coursework by the deadline at the end of Term.

20 25-2-08 to 29-2-08

What changes would you think you would make if you were going to produced several of your projects as a small business?

 

21 3-3-08 to 7-3-08

Full costing of the Project, including the cost of labour – min wage per hour rate.

 

22 10-3-08 to 14-3-08

User Guide  - A4 document

Submission of your final PowerPoint and your finished construction and User Guide and drawings

 

23 17-3-08 to 19-3-08

Easter Holidays

 

Work must be completed fully now and submitted for marking. The deadline is the end of term.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Back ] Home ] Up ] Next ]

Up
Year 7
Year 8
Year 9
Year 10
Year 11
AS Product Design
A2 Product Design
A2 Electronics